Week 1 - Partial Frame Completion and Hardware Testing
- Allison Chan
- Jan 18, 2021
- 1 min read
Updated: Jan 21, 2021
The assembly the machine has begun. A small challenge we had was that the extrusion profile of the didn't fit the T-nuts we got. However, it has been solved by custom printing 3D mounting brackets.

Electronics testing has started based on the parts we received. Testing was done on the power supply, and testing of the solenoid, ramp board, and motors are expected to be completed next week.